Before buying land in France, the question that matters is not "how big is it" but "what can I do with it".

The answer is not at the cadastre, nor at the land registration service. It is at the town hall (mairie), in a free document that two people out of three request in the wrong version.


Two certificates that answer different questions

The CUa tells you that you are in zone UB. The CUb tells you whether the 140 m² house you have in mind, in that spot, with that access, can be built.

If you are buying to build, the CUb is the one you need.


The deadlines

TypeProcessing time
Information CU (CUa)1 month
Operational CU (CUb)2 months

Both are free. All they cost is time, which is precisely why you should request them early, not the week before signing.


The effect almost nobody uses

This is the most interesting part, and the least known.

A certificat d'urbanisme freezes the rules for 18 months: the planning provisions, the tax regime and the contributions applicable to the land cannot be called into question during that period, with limited exceptions.

The certificate can also be extended, on request, if the rules have not changed.


What to attach

For a CUa: the identification of the land (commune, section, parcel number) and a location plan.

For a CUb you also need to describe the project: the kind of construction planned, its use, approximate floor area and where it sits on the land. You do not need a full building permit application, but a vague description gets a vague answer.

The application goes to the town hall of the commune where the land is, or online in communes that offer it.


What it does not do

It is not a building permit. A positive CUb does not exempt you from applying for a permit (permis de construire).

It says nothing about ownership. To know who owns the land and what weighs on it, you need the land registration service (service de publicité foncière). The état hypothécaire explained.

It says nothing about the ground. Pollution, natural hazards, geotechnical conditions: those are other assessments, and some are compulsory when selling.


The logical order before buying

  1. CU: does the land allow what I want to do?
  2. État hypothécaire: who owns it, and what weighs on it?
  3. État des risques: compulsory for a sale, and free to produce. More on the ERRIAL
  4. Bornage, if there is any doubt about the boundaries

The first is free and takes one to two months. That is why it has to come first, not last.


The starting point

All of these procedures start with the parcel's cadastral identification: commune, section, number. Without it the town hall cannot process anything.

The French cadastral map gives it to you when you click the parcel: full reference, GPS coordinates and boundaries visible on the aerial photo, before you have even set foot in the town hall. On a site visit, the Catastro GPS app shows you where the parcel lines run around you.